Category Sand Rails Access Work Update Show all
-
Sand Rails Access Work Update - 2 June 2025
Share Sand Rails Access Work Update - 2 June 2025 on Facebook Share Sand Rails Access Work Update - 2 June 2025 on Twitter Share Sand Rails Access Work Update - 2 June 2025 on Linkedin Email Sand Rails Access Work Update - 2 June 2025 linkCormac have been continuing to work on the sand tram way sloping revetment by dismantling the old structure and re-building the revetment with a concrete foundation. They are also providing drainage to the structure - something that the original revetment lacked.
The old revetment blockwork has been removed and sorted, with the intention to re-use as much of the original blockwork as possible.
After weeks of good weather, the recent change in weather has proved challenging. Recent high tides have also prevented work on the lower section of the revetment at times. However, works have proceeded elsewhere on site.
The next week's work will focus on the rebuilding of the short wall next to the siding higher up the revetment, whilst waiting for the delivery of the tramway replacement rails.
-
Sand Rails Walkway – Why the Work Was Needed
Share Sand Rails Walkway – Why the Work Was Needed on Facebook Share Sand Rails Walkway – Why the Work Was Needed on Twitter Share Sand Rails Walkway – Why the Work Was Needed on Linkedin Email Sand Rails Walkway – Why the Work Was Needed linkIn May 2023, the lower section of the sand railway walkway near Summerleaze was closed on public safety grounds due to significant erosion caused by wave action. Inspections revealed two main issues:
- The canal wall between the walkway and the river had been weakened by wave damage, including the loss of mortar and the formation of voids (holes).
- The walkway surface itself had become uneven and unsafe, particularly for those using wheelchairs, pushchairs or with limited mobility.
Early in 2025, Cornwall Council commissioned essential repair works to stabilise the canal embankment. This included filling identified voids and repointing missing mortar along the sea wall. These initial repairs were funded through Cornwall Council’s capital maintenance budget.
What Happens Next?
Further improvement works to the walkway are now part of Future Coast Bude, supported by funding from Defra as part of the Coastal Transition Accelerator Programme (CTAP). Future Coast Bude is one of several projects across England being delivered under the £200 million Flood and Coastal Innovation Programme, managed by the Environment Agency.
The additional funding will allow:
- Resurfacing of the walkway to provide safer and more accessible access to the beach
- Preservation of key historic features where possible
- A broader review of land use along the beachfront at Crooklets and Summerleaze in light of future coastal change
Work to resurface the walkway is being carried out by Cormac, with completion expected before the 2025 summer holidays.
If you have any questions about this work, please contact: futurecoastbude@cornwall.gov.uk