Sand Rails Access Work Update - 16 June 2025

Works on site are progressing, with further courses of reclaimed blockwork being added to the sloping revetment. Due to the linear nature of the site and to reduce manual handling, the revetment is being built up in layers from the seaward end first.
The works for the next week involve:
- Continued rebuilding of the revetment
- The addition of scaffolding to aid access to the working areas
- Rebuilding works planned for the short retaining wall.
- Replacement rails are expected to be delivered and will require the application of a corrosion resistant paint in order to extend their lifespan before their eventual installation.
![]() |
![]() |
![]() |
Excavated revetment material being sorted for reuse to rebuild wall. |
Further courses of block work being added to the sloping revetment. |
Removal of old retaining wall and fresh foundation ready. |