Sand Rails Access Work Update - 23 June 2025

Progress continues on site as work moves into the next phase. Materials are being prepared, key features are taking shape, and the team is making use of specialist techniques to support the restoration.

Take a look at this week’s images for a snapshot of what’s happening.

Stone from Pigsdon Quarry is being mixed with
the existing stones to ensure enough stones are available for the work.
A temporary scaffolding deck has been installed to give access further up the revetment.
The revetment section has been completed and is being pointed in Marine mortar. Setting out for the ‘dwarf wall’ has been completed.
The replacement “sand rails” have been delivered, for use where the existing ones are in poor condition. These have been painted with a special paint to help preserve them.




Categories: Sand Rails Access Work Update