Sand Rails Access Work Update - 30 June 2025
Progress on the access way has been progressing well and another level of scaffolding has been installed to give access to higher up the revetment. This section of revetment has now been completed and pointed with Marine mortar. Progress has also been made on the dwarf wall.
![]() |
![]() |
![]() |
![]() |
Second level of scaffolding | Pointing of the wall. | Progress on dwarf wall | The rails have been painted with galvanised paint. |