30th April 2026

The project team continues to work hard on site with the aim of providing temporary pedestrian access over Ross Bridge from the close of Friday 1st May, in time for the early May Bank Holiday weekend. Momentum remains strong, and good progress is being made, with both the main works team and the mechanical & electrical contractors fully focused on completing the remaining tasks needed to make the temporary access available safely.

Pedestrian access will close again on Tuesday 5th May so that construction work can safely continue. Due to the close proximity of pedestrians to heavy plant and machinery, no construction work will take place over the Bank Holiday weekend, for safety reasons.