We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Ross Swing Bridge refurbishment, Penzance
commencing 5th January 2026 for thirteen weeks
Share Ross Swing Bridge refurbishment, Penzance
commencing 5th January 2026 for thirteen weeks on FacebookShare Ross Swing Bridge refurbishment, Penzance
commencing 5th January 2026 for thirteen weeks on TwitterShare Ross Swing Bridge refurbishment, Penzance
commencing 5th January 2026 for thirteen weeks on LinkedinEmail Ross Swing Bridge refurbishment, Penzance
commencing 5th January 2026 for thirteen weeks link
In September 2024 a Principal Inspection of the bridge was carried out, which revealed that areas of the steel-work required repair and repainting. Although some areas were in better condition than others, it was determined that the entire steel-work on the structure must be refurbished.
The bridge will be dismantled and the existing concrete deck removed for recycling. The steel-work structure will be lifted on to a barge using a crane, then transported by sea to a dry dock facility at Falmouth, for specialist refurbishment. This will include inspection and maintenance of the hydraulic mechanisms which are used to shift lift and rotate the bridge in and out of position, shot blasting, refurbishment and repainting of the steel structure, masts, and stays, and new steel parapets and a new footway will be fabricated. The structure will then be transported back to Penzance, to be assembled and lifted back in to place, before resurfacing and the reinstatement of the pedestrian footway.
Keeping Penzance Moving - Road Closures Whilst the refurbishment is underway, a temporary bridge will be installed, providing a single lane for vehicles (managed by traffic lights) with pedestrian access. However, road closures will be required for both the initial and final 3-4 week periods, to allow the bridge to be removed and the temporary one assembled, then vice versa. Short-term closures will also be needed periodically during the program, to enable the temporary bridge to be lifted, so that boats can access the dry dock.
Advanced warning signs will be in place ahead of each closure, together with a fully signposted diversion route (highlighted here in green).
The Dry Dock and other nearby businesses remain open as usual, throughout the project.
Regular updates will be available on this page throughout the project.
Disconnect utilities, lighting & cabling etc, remove deck & non structural components, remove weighting systems and connections and prepare for lifting.
WEEK 2
WEEK 3
Controlled lift & removal for refurbishment. Lift temporary bridge in to place.
WEEK 4
Install and connect temporary bridge.
WEEK 5
ROAD OPEN
Single lane for vehicles, with two-way traffic lights and pedestrian access. Periodic short-term road closures to be advised, to allow lifting of the temporary bridge, giving access to the dry dock as required. Clearly signposted diversion route will be in place.
WEEK 6
WEEK 7
WEEK 8
WEEK 9
WEEK 10
ROAD CLOSED
Preparation and disassembly of the temporary bridge, in readiness for it's lifting and removal.
WEEK 11
WEEK 12
Install and connect refurbished bridge. Install deck and new surface. Carry out testing & certification in readiness for opening.
WEEK 13
WEEK 14
ROAD OPEN
Open and return to normal service.
NB Actual dates are to be confirmed and will be subject to change.
In September 2024 a Principal Inspection of the bridge was carried out, which revealed that areas of the steel-work required repair and repainting. Although some areas were in better condition than others, it was determined that the entire steel-work on the structure must be refurbished.
The bridge will be dismantled and the existing concrete deck removed for recycling. The steel-work structure will be lifted on to a barge using a crane, then transported by sea to a dry dock facility at Falmouth, for specialist refurbishment. This will include inspection and maintenance of the hydraulic mechanisms which are used to shift lift and rotate the bridge in and out of position, shot blasting, refurbishment and repainting of the steel structure, masts, and stays, and new steel parapets and a new footway will be fabricated. The structure will then be transported back to Penzance, to be assembled and lifted back in to place, before resurfacing and the reinstatement of the pedestrian footway.
Keeping Penzance Moving - Road Closures Whilst the refurbishment is underway, a temporary bridge will be installed, providing a single lane for vehicles (managed by traffic lights) with pedestrian access. However, road closures will be required for both the initial and final 3-4 week periods, to allow the bridge to be removed and the temporary one assembled, then vice versa. Short-term closures will also be needed periodically during the program, to enable the temporary bridge to be lifted, so that boats can access the dry dock.
Advanced warning signs will be in place ahead of each closure, together with a fully signposted diversion route (highlighted here in green).
The Dry Dock and other nearby businesses remain open as usual, throughout the project.
Regular updates will be available on this page throughout the project.
Disconnect utilities, lighting & cabling etc, remove deck & non structural components, remove weighting systems and connections and prepare for lifting.
WEEK 2
WEEK 3
Controlled lift & removal for refurbishment. Lift temporary bridge in to place.
WEEK 4
Install and connect temporary bridge.
WEEK 5
ROAD OPEN
Single lane for vehicles, with two-way traffic lights and pedestrian access. Periodic short-term road closures to be advised, to allow lifting of the temporary bridge, giving access to the dry dock as required. Clearly signposted diversion route will be in place.
WEEK 6
WEEK 7
WEEK 8
WEEK 9
WEEK 10
ROAD CLOSED
Preparation and disassembly of the temporary bridge, in readiness for it's lifting and removal.
WEEK 11
WEEK 12
Install and connect refurbished bridge. Install deck and new surface. Carry out testing & certification in readiness for opening.
WEEK 13
WEEK 14
ROAD OPEN
Open and return to normal service.
NB Actual dates are to be confirmed and will be subject to change.
Page last updated: 16 Dec 2025, 04:17 PM
History
Ross Swing Bridge connects Penzance town centre to the harbour area. Constructed in the early 20th century from an old railway turntable. it's primary function was to allow road traffic and pedestrians to cross the inner harbour, whilst enabling boats and small vessels to pass through when swung open.
In 1980 it replaced with a newer structure and is currently used by the public and to allow boats access to the dry dock and inner basin. Today the bridge remains a functional heritage structure and is still used for harbour operations as well as being a vital link fro traffic and pedestrians.
The bridge is exposed to harsh marine conditions, which cause corrosion and mechanical wear over time. A regular inspection and maintenance program is in place to keep it safe and operational, ensuring it serves the harbour for generations to come.