27th August 2026

Following a materials supply delay at the pedestrian crossing at Station Road, works here are suspended temporarily and we are scheduled to return in early September. Saracen Place will be temporarily reinstated, and the site team demobilised from site at the end of this week, pending a date from National Grid for a new connection. We can then return to site for a few days to excavate the joint pit for National Grid, then reinstate after their works are complete.

On the 7th September, we’ll restart works at Quay Hill and commence nighttime works at Treliever Road.

Share 27th August 2026 on Facebook Share 27th August 2026 on X (formerly Twitter) Share 27th August 2026 on Linkedin Email 27th August 2026 link