10th July 2026

Works are progressing well at Station Road and the kerb realignment for the foot-way crossing-points has been completed, together with the underground service ducting for electrical and communications cables.that will power the pedestrian crossing. Surfacing is underway and will be completed today, 10th July - which will allow for new road markings to be applied next week. Installation of tactile paving for the crossing points will also commence next week.

At Quay Hill the kerb realignment has been completed and tactile paving installed, and we now await delivery of the granite kerbs.

We're not yet able to commence at Saracen Place, but will begin here as soon as the traffic management restrictions on Station Road have been lifted.