Sand rails access way update - 31 July 2025
![]() |
![]() |
![]() |
![]() |
Sloping revetment almost completed to its full height. |
Sloping revetment almost completed to its full height |
Revetment and dwarf wall interface awaiting pointing |
New temporary access staircase installed for increased summer holiday foot traffic |
Works have been progressing well on site with the revetment and dwarf retaining wall almost complete. The final pointing works are left to undertake.
Works are now progressing onto the sand rail walkway, where efforts will be made to preserve the historic granite setts of the old railway siding. Works will be undertaken to provide new walkway surfacing, incorporating the historic sand rails. Where the condition of the rails is too poor to allow their incorporation into the new surfacing, they will be replaced with replica narrow gauge train rails.
The new temporary set of stairs has now been installed to ease the expected increased summer holiday foot traffic visiting Summerleaze beach. The temporary stairs will remain in place until the works on the walkway are complete.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends