Phase One - 27th February 2026

Following removal of the surfacing, our engineers have now completed a full assessment of the exposed bridge deck. A small number of areas have been identified as needing repair, and this work is scheduled to take place over the coming week.


Once these repairs are complete, we’ll begin the next sequence of works, including priming the bridge deck, applying the new waterproofing system, installing the kerb and then resurfacing the deck. This will complete the first phase of the programme and we’ll then move on to the next section of the bridge and repeat the process.