24th April 2026
Final surfacing works have now been completed on this first phase of the Camel Viaduct refurbishment. As a result, the safety barriers and current traffic management arrangements will be removed by the end of today, meaning that the Camel Viaduct will be open to two-way traffic as usual throughout the weekend. At this stage, there will be no permanent road markings in place, but the road will be fully open for vehicles in both directions, with signage in place.
After the weekend, temporary two-way traffic lights will be reinstated for a short period, to allow the team to safely undertake ducting works and complete the road markings. These activities are planned to take place early next week and are expected to be completed by close of Friday 1st May, after which the traffic lights will be removed again.
We appreciate everyone’s continued patience while these final elements are completed.