Following assessment of the exposed bridge deck, all identified areas requiring repair have now been completed. Our team has since applied the primer, and the waterproofing process is now underway. As you would expect, progress now is fully dependent on suitable weather conditions. In particular, wind, rain and dew point can all affect the application and even distribution of the spray‑applied waterproofing system. We are closely monitoring conditions to ensure each stage is carried out safely, efficiently and to the required standard.
Kerbs are already on site and ready for installation. As soon as the waterproofing is fully complete and cured, we will begin reinstating the footway.