Camborne Town Deal Transport Schemes
Latest news
Update on Camborne Town Deal Transport projects March 2025
Camborne LifeCycle
Significant progress is being made on delivering this scheme which, when complete, will provide 3.7km of enhanced walking and cycling routes with the aim of connecting key sites and encouraging pedestrians and cycle usage, cutting down on car journeys and improving air quality in and around the town centre.
The scheme covers 8 separate locations with a variety of measures to enhance walking and cycling provision from the town centre, along the former Roskear tramway with connections to Park Gerry and the Red River Trail.
Roskear route :
Construction of the works at the first location at Rosewarne Road were completed in January. These included widening the existing footway on the east side of the road and installing a dropped crossing point with tactile paving to improve accessibility between Rosewarne car park and the centre of the town. A new streetlight was also installed as part of the scheme.
Work is now continuing at other locations which includes sections of the Roskear Tramway and North Roskear Road.
Tramway wall – following concerns over the condition of a section of the supporting wall on the Tramway, an assessment was carried out which concluded that without immediate repairs there was a significant likelihood that the Tramway may need to be closed to users. To avoid this taking place, members of the Town Deal Board agreed to allocate funding to carry out the repairs. The structure of this section of the wall has been a problem for some considerable time and the decision of the Board to meet the costs of the repairs has been welcomed by the local community.
Work to repair the affected section began on 18 February and is being carried out by Cormac.
It has also been agreed to provide an additional £500,000 to enable further improvements to be carried out on the Tramway and surrounding network.
This follows a report into the escalating costs of remediating complex mining related infrastructure at Treverno park on Boilerworks Road. This report identified a £500,000 shortfall in the funding needed to carry out the remediation works that would allow a new footway to be constructed. Despite extensive efforts by Cornwall Council and the Town Deal transport project team, it has not been possible to identify any additional funding at this time.
As a result, the Board has endorsed a recommendation to remove the Treverno scheme from the Town Deal programme and redistribute the £500,000 budget to support additional works on the wider Roskear route.
The details of how this will be allocated are still being considered but are likely to include further surfacing and drainage improvements to the Roskear Tramway, carrying out further works to improve access for pedestrians and cyclists and providing additional signage and street furniture.
Cornwall Council would continue to explore other funding options for the Treverno scheme beyond Town Deal.
The overall Camborne LifeCycle programme remains on schedule, with the first tranche of the construction works due to be completed before summer 2025 and the second portion of works to be delivered by early 2026.
Camborne Renew
This scheme is designed to enhance the appearance of Camborne town centre, improve access for pedestrians and cyclists, and increase the amount of time people spend in the town and support the local economy.
Following the completion of detailed designs for the scheme, the plans were published for formal consultation at the end of January. These included proposals to improve the environmental aspect of the town centre by adding more seating and plant greenery, improved pedestrian crossings, extending on-street parking at the top of Trelowarren Street to 1 hour and enhanced lighting and CCTV. There were also proposals to enhance the character of adjoining streets to complement the overall scheme.
The consultation has now closed and the project team are currently reviewing the feedback from the local community.
A report setting out the results of the consultation, with recommendations on the way forward for the scheme, will be considered by members of the Camborne Town Deal Board.
Subject to the results of the consultation, it is anticipated that construction will begin in the summer 2025.
Visualisation - Trelowarren Street looking towards Commercial Square
Visualisation - Chapel Street looking north towards Commercial Square
Information about the wider Camborne Town Deal Transport Project is also available on the Camborne Town Deal website. P
December 2024
Camborne LifeCycle:
Work is progressing on site to deliver the Camborne LifeCycle scheme.
LifeCycle Camborne has been awarded £1.643m of Town Deal funding, with match funding of £325,500 from Cornwall Council which is leading the project. Connecting central Camborne to the Red River and the Great Flat Lode, the project will provide 3.7km of enhanced walking and cycling routes with the aim of encouraging pedestrians and cycle usage, cutting down on car journeys and improving air quality in the town centre. There are schemes taking place at eight separate locations.
Construction works started at Rosewarne Road on November 18th and have progressed along the route to Roskear Road. The scheme includes widening the existing footway on the east side of the road and installing a dropped crossing point with tactile paving. The aim is to improve accessibility between Rosewarne car park and the centre of the town for residents and visitors to the area, including those with wheelchairs or prams, and the partially sighted. A new streetlight will also be installed as part of the scheme.
The scheme is being constructed by Cormac, with traffic lights in use during the duration of the works to enable the team to work safely
Construction delivery for Camborne LifeCycle is on programme, with the first portion of the construction works due to be completed before summer 2025 and the second portion of works to be delivered by early 2026.
You can find out more on the Camborne Town Deal website : https://cambornetowndeal.com/life-cycle-camborne-cycling-and-walking-network/
Camborne Renew:
This scheme aims to enhance the appearance of the town centre, improve access for pedestrians and cyclists, and increase the amount of time people spend in the town, supporting the high street economy. It is not about pedestrianisation and banning cars, or reducing the number of car parking spaces available to high street users.
Following feedback from the public consultation held in 2023, which raised objections to proposals to alter existing traffic flow within the town centre, revised plans were drawn up. These focus on improving the environmental aspect of the town centre by adding more seating and plant greenery, better pedestrian crossings and providing up to 60 minutes of free parking at the top of Trelowarren Street and secure cycle parking.
Camborne Renew is in the final stages of the detailed design. The project team are working hard to develop a scheme that delivers change, aligns with the project budgets and provides minimum disruption during the construction phase.
The underground utility survey has posed a number of engineering challenges to the scheme with alternative solutions required. Further traffic speed surveys have been undertaken as well as accessibility audits. Road coring and utility trial pits will be undertaken in the new year to confirm some of the more challenging aspects of the design and to confirm the pavement calculations.
The project team are aiming to complete design shortly. The scheme will then undergo the public statutory consultation in the new year.
Once the materials and designs have been agreed, work will take place to carry out the technical construction design and finalise the traffic management arrangements to support the construction phase.
The project team are very aware of concerns over the potential impact of some elements of the Renew scheme on businesses in the town centre and are working closely with partners and local stakeholders to ensure that any disruption is kept to a minimum.
While some diversions will need to be put in place during the construction period, these will be carefully planned in consultation with the local community during the coming months.
2024 Online Public Exhibition
Camborne residents were asked for their views on revised proposals to improve public spaces and the way people travel around the town centre. The consultation concluded on the 15th May 2024.
The Camborne Renew project has been amended to reflect the views of those who took part in a public consultation last year and the plans are now available to view online and at Council Offices, Dolcoath Ave, Camborne TR14 8SX .
Changes made as a result of previous resident feedback include:
- there will be more seating and plant greenery in the town centre;
- additional zebra crossings will be installed on Trelowarren Street and Commercial Street ;
- 125 spaces within close proximity to Trelowarren Street will offer free parking for up to an hour, and;
- there will be secure cycle parking in the town.
Earlier proposals for altering the flow of traffic along Trelowarren Street will now no longer take place.
2023 Exhibition Feedback
Thank you to everyone who took the time to view and comments the designs presented at the end of May. The survey results can be viewed here (or you can download a copy in the document section on this page)
Following review of the survey results, the proposals aiming to improve public spaces and the way people travel around Camborne Town Centre were amended to reflect the views of local residents.
Changes made as a result of feedback from the consultation include:
- proposals for altering the flow of traffic along Trelowarren Street will now no longer take place;
- there will be more seating and plant greenery in the town centre;
- additional pedestrian crossings will be installed;
- the parking bays at the top of Trelowarren Street will offer free parking for up to an hour, and;
- there will be secure cycle parking in the town.
You can view a short video on YouTube here:
About the Project
The aim of the Camborne Town Deal transport schemes is to enhance the appearance of the town centre and provide benefits for walking and cycling within the town.
LifeCycle Camborne scheme – connecting central Camborne to the Red River and the Great Flat Lode, this scheme will provide 3.7km of enhanced walking and cycling routes with the aim of encouraging pedestrians and cycle usage, cut down on car journeys and improve air quality in the town centre. These also include connections to Park Gerry (a Town Deal project) and improved links to Roskear School.
Camborne Renew scheme - this forms part of the Camborne Town Deal Board’s vision to regenerate the heart of Camborne and transform it into a visually appealing, accessible place to live, work, shop and visit.
The Camborne Renew project is about:
- Enhancing the appearance of the Town Centre
- Encouraging longer dwell time thereby supporting high street economy
- Providing a welcoming and safe environment for all users of the town
- Supporting and adding value to the other Town Deal projects
The Camborne Renew is not about:
- Pedestrianisation and banning cars
- Reducing the number of car parking spaces available to high street users
Delivered by Cornwall Council, the team leading on the Camborne Renew project, are working with community groups through 2024 to finalise the project designs.
About the Camborne Town Deal
Camborne has been allocated up to £23.7 million from the Government's Town Deal Fund to support 11 capital projects that will improve the town’s prosperity, infrastructure and sustainable economic growth.
The Camborne Town Deal programme is supported by a group of volunteers who help to lead the process of preparing and implementing the Town Investment Plan.
The board is composed of a mix of representatives from the private, public and community sectors who are committed to improving their local area. Members of the boards include local businesses, community stakeholders, Councillors from Cornwall Council and Town Council, and the area’s MP.
For more information about the 11 Town Deal funded projects please visit: Camborne Town Deal website
You can also follow the Camborne Town Deal programme on social media.